How much does it cost to open a gas station in Mexico?
Honest ranges, by line item and by scenario. Most websites hide these figures; we would rather you come into your project with realistic expectations.
New station: investment by line item
| Line item | Estimated range (MXN) |
|---|---|
| CNE permit filing fee | ~ $32,081 |
| Technical and environmental studies (MIA, ARSH/PRESH, LAU, SASISOPA) | $350,000 – $500,000 |
| Municipal licenses (land use, construction, civil protection) | Varies by municipality |
| Civil works, tanks and dispensers | $3,000,000 – $4,200,000 |
| End-to-end regulatory management fees | Based on scope |
Typical total: between $3.5 and $5 million pesos. The site and the construction drive the variation; permitting is the small part of the cost — and the part that stops the most projects when it is done wrong.
Build your investment range
Check what applies to your project. We add up only the ranges published above — the result is always a range, not a quote.
Plus the variable line items you checked (municipal licenses and management fees), which depend on your case.
Want the number for your own scenario? Request an assessment.
Not every project starts from zero
New station
The full scenario: site, three authorities, construction and equipment. The right sequence ("paperwork before concrete") is what protects the investment.
See the guide to opening a station →Site or business conversion
It saves on construction but not on permitting: the CNE + ASEA documentation is the same, and land-use approval can be the bottleneck.
Request a feasibility assessment →Regularizing a station already in operation
Regularization — bringing an existing station into compliance — costs a fraction of opening, and it avoids fines of up to 50,000 days' wages. The RENAGAS window lowers the cost of getting current.
See how regularization works →Idle construction is the expense nobody budgets for
Building before you hold the permit means paying financing on infrastructure that cannot operate. A deficiency notice on poorly assembled documentation (an RFC missing its homoclave, a shapefile not in WGS-84, an expired insurance policy) can stall the project for months — with the tanks already bought.
That is why the right schedule matters more than any single line of the budget: paperwork before concrete.
Frequently asked questions
Indicative figures as of 2026, in Mexican pesos; they depend on the site, the municipality and the authority. They do not replace a formal quote.
Size your investment with figures from your own scenario
Tell us the site, the municipality and the stage: we send back an honest estimate of investment and timelines for your case.
Request your assessment