Guide · Current framework

Looking for the CRE permit? You now file it with the CNE

The Energy Regulatory Commission (CRE) was replaced by the National Energy Commission (CNE). The permit you need still exists — what changed is the authority and the process, not the obligation. Here is what you need to know.

The change

What the reform changed (and what it didn't)

Changed
  • The authority: the CNE takes over the CRE's permitting functions.
  • The process: the application is filed through SENER's Ventanilla Única de Energía (the single-window energy portal), mostly online.
  • The terminology: what you used to look up as a "CRE permit" is today the CNE permit for marketing or retail sale of refined petroleum products.
Unchanged
  • The obligation: without a permit, no purchase or sale of fuel is legal.
  • Existing permits: the ones issued by the CRE remain valid and in force.
  • The substantive documentation: technical, tax and legal requirements are still the hard part of the filing.
Your situation

What to do in your case

I'm opening a new gas station

You file for the fuel marketing/retail permit directly with the CNE, along with the ASEA documentation and the municipal permits.

Start with the guide to opening a gas station →

I hold a permit issued by the CRE

It's still in force. Amendments, permit transfers and recurring obligations (such as volumetric reports) are now filed with the CNE.

See our CNE permit service →

My documentation stalled halfway with the CRE

Filings in progress moved to the new framework. It's worth checking the status in the Ventanilla Única and revalidating the documentation before reactivating it.

Request a status assessment →

I'm operating out of compliance (expired licenses)

The transition does not erase obligations: ASEA-PROFECO inspections continue. Regularization — bringing an existing station into compliance — is dramatically cheaper before an inspection visit.

Learn about RENAGAS regularization →
What people ask

Frequently asked questions

Yes. Under the 2024-2025 energy reform, the Energy Regulatory Commission (CRE) was replaced by the National Energy Commission (CNE), which now carries out its permitting functions.

Yes. Permits granted by the CRE remain valid and in force; later filings (amendments, permit transfers, reports) are now made with the CNE.

With the CNE, through SENER's Ventanilla Única de Energía portal, in a mostly digital process.

The obligation to hold a permit did not change. The process is more digital and a new authority runs it; the substantive requirements (technical, tax and legal documentation) stay the same, and it's worth checking them against the regulations in force before you file.

General guidance, updated for the CNE framework now in force. It does not replace formal advice; always check against DOF and official sources.

Initial assessment

Not sure where your permit stands?

We'll tell you exactly which authority your filing sits with today, what obligations are outstanding and how to get current.

Regulation and energy under one roof
Follow-through to the final decision
Response in under 24 business hours

Request your assessment

Response in under 24 business hours.

General guidance; it does not replace formal advice.

Cookie Preferences

Choose which cookies you allow. Essential cookies cannot be disabled as they are required for the site to function. Learn more.

Essential

Authentication, security, and core site functionality. These cannot be disabled.

Analytics

Help us understand how visitors interact with the platform so we can improve it.

Marketing

Used to deliver relevant content and measure the effectiveness of campaigns.