Updated · October 2026 · CNE framework

How to open a gas station in Mexico: 2026 permits

Opening a gas station is no longer a leap of faith. This guide puts the three key filings in order — the energy permit from the CNE (formerly CRE), the ASEA documentation and the municipal permits — with costs, timelines and the schedule that protects your investment.

By the Regenera team · hands-on experience with multi-authority permits in the energy sector

$32,081
CNE filing fee (MXN)
90
Business days for a CNE decision
3
Authorities: CNE · ASEA · Municipality
30
Years the permit stays valid
The new landscape

From the CRE to the CNE

Under the 2024-2025 energy reform, the functions of the Energy Regulatory Commission (CRE) moved to the new National Energy Commission (CNE). If you searched for a "CRE permit", the filing still exists, but today it is the CNE that decides it, through SENER's Ventanilla Única de Energía (the single-window energy portal). What changed is the authority and the process (more of it online), not the obligation to obtain the permit. Read the details of the CRE → CNE transition.

To sell a single liter of gasoline or diesel you have to put together three sets of documentation before three separate authorities. Taking them out of order is the most expensive mistake in the project.

The documentation

The three authorities you have to answer to

1

CNE · Energy

The Marketing or Retail Permit for Refined Petroleum Products is the "key" to the business: without it, no purchase or sale of fuel is legal. Filed online, valid for 30 years, decided in up to 90 business days.

We handle your CNE permit →
2

ASEA · Environment

An agency under SEMARNAT. Requires an MIA, an Operating License, the LAU (up to 70 business days), SASISOPA, RENAGAS registration and risk studies (ARSH/PRESH).

See our ASEA compliance service →
3

Municipality

Grants compatible land use, the building permit and the civil protection sign-off. It is the first filter: if the site is not viable, everything else stops.

Investment

How much does it cost to open a gas station?

Estimated investment by line item (2026)
Line item Estimated range (MXN)
CNE permit filing fee~ $32,081
Technical studies and local licenses (MIA, LAU, SASISOPA, ARSH, municipal licenses)$350,000 – $500,000
Civil works, tanks and dispensers$3,000,000 – $4,200,000
Fees for end-to-end regulatory managementDepends on scope

With a net margin close to $1.50 per liter and a conservative volume of 250,000 liters/month, payback is usually reached between the fourth and fifth year; a convenience store speeds up the return. Break down your investment by scenario.

Schedule

Paperwork before concrete

1

Validate the site and assemble the documentation

Weeks 1-2: confirm compatible land use and assemble the digital and tax documentation (positive SAT compliance opinion, no partners on the 69-B list).

2

Arrange storage and insurance

Weeks 3-4: sign storage contracts and take out insurance policies; start the MIA and the risk studies.

3

File the application with the CNE

Week 5: file the marketing/retail permit application through the Ventanilla Única de Energía.

4

Compile the ASEA documentation

Weeks 6-12: move ahead with light site work (clearing, grading) while the CNE reviews; compile the Operating License, the LAU and SASISOPA.

5

Handle the inspection

Weeks 13-14: handle the inspection with tanks and dispensers ready to operate.

Why the order matters: following this sequence keeps you from carrying financing costs on infrastructure that cannot operate yet. Idle construction is the invisible cost that sinks the profitability of poorly planned projects.

Heads up

Common mistakes that trigger deficiency notices

  • RFC without its homoclave suffix, or details that do not match the articles of incorporation.
  • Site shapefile in a projection other than WGS-84 (the CNE accepts WGS-84 only).
  • Liability insurance policy with no effective start date.
  • Starting major construction before holding the permit, which leaves you with idle construction.
Don't mix them up

Franchise vs permit

Franchise

Brand agreement

Pemex, G500, Mobil, BP, Oxxo Gas. It defines branding, supply and commercial terms. It does not legally authorize you to sell fuel.

CNE permit

Legal requirement

It is the government's authorization to market refined petroleum products. Essential, with or without a franchise. You can operate under your own brand if you hold it.

Compare franchise vs your own brand in detail.

After you open

The permit is the start, not the finish

You will have to file volumetric reports, the Annual Operating Report (COA) and emissions monitoring (form FF-ASEA-06), and keep licenses and SASISOPA current. NOM-005-ASEA-2016 governs the operation and maintenance of stations, and PROY-NOM-023-ASEA-2025 (out for public comment) will replace it with new requirements. Set up your ongoing compliance plan.

Watch out for a closure order: close to 60% of stations operate with an expired license or outside RENAGAS. Joint ASEA-PROFECO inspections can lead to fines of up to 50,000 days' wages and suspension of operations. Bring your station into compliance.

Common concerns

Frequently asked questions

No. The CRE's functions moved to the CNE; today the marketing/retail permit for refined petroleum products is filed with the National Energy Commission.

The filing fee is around $32,081 MXN; total investment to open a station usually falls between $3.5 and $5 million, depending on the site and the construction work.

The CNE decides in up to 90 business days; the LAU with ASEA takes up to 70 business days. Timelines depend on each authority.

No. A franchise is a brand agreement, separate from the legal permit from the CNE. You can operate under your own brand if you hold the permit.

Official sources

General information, current as of October 2026. It does not replace formal regulatory advice; timelines and amounts depend on the authority and can change.

Initial assessment

Ready to open your gas station without surprises?

Get your personalized CNE + ASEA + municipal roadmap, with estimated time and cost.

Regulation and energy under one roof
Follow-through to the final decision
Response in under 24 business hours

Request your assessment

Response in under 24 business hours.

General guidance; it does not replace formal advice.

Cookie Preferences

Choose which cookies you allow. Essential cookies cannot be disabled as they are required for the site to function. Learn more.

Essential

Authentication, security, and core site functionality. These cannot be disabled.

Analytics

Help us understand how visitors interact with the platform so we can improve it.

Marketing

Used to deliver relevant content and measure the effectiveness of campaigns.